KCNNinh Binh

RANG DONG TEXTILE INDUSTRIAL PARK - NINH BINH

1 photos

Key facts

Total area
322 ha
Rent
Not updated
Occupancy
100%
Year established
2015
Investor
Not updated
Management unit
Not updated

Overview

RANG DONG TEXTILE INDUSTRIAL PARK - NINH BINH 

Address: Nghia Hung District, Ninh Binh Province 

Operating Period: 2015 - 2065

Total Area: 322 hectares

Rental Price: 85 - 95 USD/m²/lease cycle (excluding VAT, includes land tax paid for the entire lease period).

Strategic Location and Regional Connectivity

l About 10 km from Hai Thinh Port;

l About 140 km from Hai Phong Port;

l About 200 km from Cai Lan Port;

l About 150 km from Nghi Son International General Port;

l About 55 km from Nam Dinh city center;

l About 150 km from Hanoi city center;

l About 40 km from Ninh Binh city center;

l About 75 km from Thai Binh city center;

l About 150 km from Noi Bai Airport;

l About 145 km from Cat Bi Airport.

l Rang Dong Textile Industrial Park is situated on the route connecting the Hanoi-Ninh Binh Expressway to Nam Dinh (connecting point at the Cao

Bo interchange in Y Yen District, Nam Dinh Province). It is also located along the coastal economic route connecting provinces from Thanh Hoa to

Quang Ninh, a key national project. The government has approved and allocated the budget for the provinces along the route to execute this

project. Additionally, the park is close to the coastal expressway connecting provinces from Ninh Binh to Hai Phong.

ng.jpg

Regional Connectivity Map of Rang Dong Textile Industrial Park

Investment-Attracting Industries in Rang Dong Textile Industrial Park

Textile-related industries, including garment production, leather goods, bags, yarn spinning, fabric weaving, printing-dyeing, accessory production,

packaging, etc.;

Industries related to building materials, light industry, supporting industries, office services, and other support services.

Infrastructure of Yen Bang Industrial Cluster

Electricity Supply: 110kV substation with a capacity of 2x63MVA; centralized boiler solution of 350T/h. Electricity is supplied at 0.4kV or 22kV

to the factory's fence.

Water Supply: Total water supply capacity of 170,000 m³/day and night.

Wastewater Treatment: Wastewater treatment capacity of 110,000 m³/day and night.

Investment Incentives in Rang Dong Textile Industrial Park

l 100% exemption of corporate income tax (CIT) for the first 2 years and a 50% reduction for the next 4 years.

l Application of a 10% CIT rate for 15 years, with a maximum 4-year tax exemption and a 50% reduction for the next 9 years for certain industries

(subject to conditions).

l Full exemption from import duties on machinery and equipment used to form fixed assets. VAT will be refunded as soon as the factory

starts operating.

Investment Support in Rang Dong Textile Industrial Park

l Free support for procedures related to investment policy approval, investor approval, obtaining Investment Registration Certificates (except in

cases where the investor needs to establish an export processing enterprise), and Enterprise Registration Certificates.

l Support services for training and recruitment;

l Access to the Aurora ecosystem, connecting with banking, tax, and other partners; support in connecting with infrastructure partners to meet

specialized needs for textile dyeing projects; and support in connecting with partners in the textile production chain.

nh.jpg

Master Plan of Rang Dong Textile Industrial Park

Investment Procedure in Rang Dong Textile Industrial Park

1. Signing the land sublease principle agreement.

2. Applying for investment policy approval, investor approval, and obtaining the Investment Registration Certificate.

3. Applying for the Enterprise Registration Certificate.

4. Signing the land sublease contract.

5. Applying for the Land Use Right Certificate.

6. Environmental procedures (registering the Environmental Protection Plan or preparing and obtaining approval for the Environmental Impact

Assessment Report).

7. Preparing and obtaining approval for the detailed master plan.

8. Preparing and obtaining fire prevention and fighting approval and basic design approval.

9. Preparing and obtaining fire prevention and fighting approval and technical design approval.

10. 

Location

Industrial Growth:Highly DevelopedDevelopingUnderdeveloped

19.9680, 106.1393

Videos of this park

Empty

This park has no videos yet

?